Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Pending Pending24
Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete 

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete 

1 weeks before any release.Anil Belur
Pick RC and produce CSIT spreadsheet

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.Daniel De La Rosa
Vet CSIT failures

Complete  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Pending 25  


TSC
Publish released artifacts to Nexus

Pending26  


Communicate Managed release to Self Managed projects

Pending 26  


Unlock stable branch

Pending26  


Anil Belur
Release All SM projects (including "official" distribution)

Pending 31 May  

Max 1 week after Managed release.All SM projects (including int/dist) Luis Gomez
Update docs

Pending  31 May  


...