Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete 

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete 

1 weeks before any release.Run the job `autorelease-gerrit-branch-lock-$RELEASE` to lock the branch for code freeze. Ref: Documentation
Pick RC and produce CSIT spreadsheet

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.Daniel De La Rosa
Vet CSIT failures

Complete 

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release
Pending27 May

Complete 


TSC
Publish released artifacts to Nexus
Pending30 May 30 May

Complete 


Communicate Managed release to Self Managed projects
Pending 

Complete  


Unlock stable branch
Pending30 May

Complete 


Anil Belur
Release All SM projects (including "official" distribution)

Pending 

02

 

Max 1 week after Managed release.All SM projects (including int/dist) Luis Gomez
Update docs

Pending  

02