Event / TimelineStatusCommentsWho
Communicate code freeze to projects
Done

Complete 

1 weeks before code freeze happens
Code freeze (stable branch lock)
Done 23

Complete  

1 weeks before any release.Anil Belur
Pick RC and produce CSIT spreadsheet
Done 23

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures
Done 26 Oct

Complete  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release
Done29 Oct

Complete 


TSC
Publish released artifacts to Nexus
Done 29 Oct

Complete 


Communicate Managed release to Self Managed projects
Done 29 Oct

Complete  


Unlock stable branch
Done 29 Oct 05

Complete  


Anil Belur
Release All SM projects (including "official" distribution)
Done  05

Complete   

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs
Done  

Complete