Communicate code freeze to projects

Complete 

1 weeks before code freeze happens
Code freeze (stable branch lock)
Pending 28

Complete  

1 weeks before any release.Anil Belur
Pick RC and produce CSIT spreadsheet
Pending 28

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures
Pending 28 Oct 29 Oct

Complete  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release
Pending29 Oct

Complete 


TSC
Publish released artifacts to Nexus
Pending

Complete 


Communicate Managed release to Self Managed projects
Pending 29 Oct

Complete  


Unlock stable branch
Pending 29 Oct 05

Complete  


Anil Belur
Release All SM projects (including "official" distribution)
Pending  05

Complete   

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs