PendingComplete


Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete 

1 weeks before code freeze happens
Code freeze (stable branch lock)
Pending 28

Complete  

1 weeks before any release.Anil Belur
Pick RC and produce CSIT spreadsheet
Pending 28

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Pending 

28 Oct

 

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Pending

29 Oct

 


TSC
Publish released artifacts to Nexus

Pending

29 Oct

 


Communicate Managed release to Self Managed projects

Pending 

29 Oct

 


Unlock stable branch

Pending 

29 Oct

 


Anil Belur
Release All SM projects (including "official" distribution)

Pending  

05

 

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Pending  

05